Costs

RENOVATIONS

Elevator Vestibule $330,000
Restroom Renovation $102,000
Kitchen Renovation $180,000
General Hall Work- Including Classroom Partitions $201,000
TOTAL RENOVATION COSTS $813,000

 

TOTAL COSTS

Renovations $813,000
Completed Roof Work $207,000
Project Shrinkage & Contingency $90,000
Interest $86,000
2008 Partners in Charity $38,000
TOTAL PROJECTED COSTS $1,234,000